Systems & Resources

Priority / Date

System

Description

Resources

 

Life Support

 

Materials

Workers

1 –end of rains

Irrigation

Installation of mainline and auxiliary lines (See site map) to support collections, catchment pond and workspaces.

Needed: 240 linear feet of mainline, pvc or copper. 12-15 valves. *Ask Berkeley Indoor Garden & Plant It Earth.*

Pond liner 2x6x8, 10 -15 rocks*, 5 bags of concrete mix.

We have 3 pumps.

Line:Multi-level team, 3-5 people. More plumbing experience the better. 8hrs

Pond: 3-5 people, carpentry & plumbing. 4 hrs

2

Soil Cycling

Vermiculture(2), compost (2) & mulch(1) beds (See schematics).

Needed:

o       1x2x18” pine/redwood slats – 64

o       4x4x12’ redwood posts – 4

o       woodscrews

 

2 teams, 2 people each, carpentry & strong helper.

6 hrs

1- ASAP

Planters/Containers

Tree planters (10),

East wall 100’ (ledge reinforcement),

vegetable beds (8)

fence planters (vines) (4)

Needed:

o       2x10”x12’ redwood planks – 30

o       concrete bolts – 50

o       4x4x12 redwood posts - 16

2 teams: cutters & assemblers

4 each, 8 hours. Mixed carpentry levels, physically strong.

 

Collections

 

 

 

3

Greenhouse

Shelves

Drainage

Door

Needed:

o       2x4x8 pine – 8

o       1.5”x 12” x 12’ pine shelving -  10

o       4-6 bags of gravel

o       curtain rod (over door)

o       heavy pvc sheeting (clear)

1 team 4 people, light carpentry.

4 hours

1

Ornamentals & Trees

Plant trees and shrubs in beds

Mulch, as much as we can get

160 feet of rip-wrap, topsoil- sandy loam, 2 pickup truck fulls

Tree team: 4 people, 4-6 hrs.

Beds

2

Biome Exploration Wall

Configure Irrigation, organize and plant ornamentals.

Needed: soil, mulch as above.

3 teams, 3 each, mixed strength,

 

Culinary Program Planting

Organize and plant seeds, seedlings

Needed: Seeds, sets, soil, mulch and fertilizer.

2 -4 teams including program participants + horticultural helpers. 4 – 8 hrs

 

Human Uses

 

 

 

 

Handwashing

Basin on pedestal by greenhouse.

Recycled, install graywater line.

1 plumber, 1 helper. 3 hrs.

 

Quiet Spaces

Benches

We have them, Place them as desired.

Teams include youth, senior, activity leaders & participants.

 

Outdoor Meeting

Tables

We have them place them as desired.

Teams include youth, senior, activity leaders & participants.

 

Mobile Stage

modules

Needed:

6 modules on casters (24)

o       2x6x12 pine – 24

o       2x4x12 pine - 18

 

2 teams: cutters & assemblers

4 people each, 8 hrs.

 

Outdoor Program Integration

Sports & other activity

Unidentified, but important needs

Teams include members of all programs.

 

SYLCentral Y Gardens Establishment Plan

Asberry Spring 2010

1 / 1


Field Notes: Need for case notes form

Thinking about confidentiality and ease of recording.

Wednesday, April 20, 2011

Assets Manager