Systems & Resources
Priority / Date | System | Description | Resources | |
| Life Support |
| Materials | Workers |
1 –end of rains | Irrigation | Installation of mainline and auxiliary lines (See site map) to support collections, catchment pond and workspaces. | Needed: 240 linear feet of mainline, pvc or copper. 12-15 valves. *Ask Berkeley Indoor Garden & Plant It Earth.* Pond liner 2x6x8, 10 -15 rocks*, 5 bags of concrete mix. We have 3 pumps. | Line:Multi-level team, 3-5 people. More plumbing experience the better. 8hrs Pond: 3-5 people, carpentry & plumbing. 4 hrs |
2 | Soil Cycling | Vermiculture(2), compost (2) & mulch(1) beds (See schematics). | Needed: o 1x2x18” pine/redwood slats – 64 o 4x4x12’ redwood posts – 4 o woodscrews
| 2 teams, 2 people each, carpentry & strong helper. 6 hrs |
1- ASAP | Planters/Containers | Tree planters (10), East wall 100’ (ledge reinforcement), vegetable beds (8) fence planters (vines) (4) | Needed: o 2x10”x12’ redwood planks – 30 o concrete bolts – 50 o 4x4x12 redwood posts - 16 | 2 teams: cutters & assemblers 4 each, 8 hours. Mixed carpentry levels, physically strong. |
| Collections |
|
|
|
3 | Greenhouse | Shelves Drainage Door | Needed: o 2x4x8 pine – 8 o 1.5”x 12” x 12’ pine shelving - 10 o 4-6 bags of gravel o curtain rod (over door) o heavy pvc sheeting (clear) | 1 team 4 people, light carpentry. 4 hours |
1 | Ornamentals & Trees | Plant trees and shrubs in beds | Mulch, as much as we can get 160 feet of rip-wrap, topsoil- sandy loam, 2 pickup truck fulls | Tree team: 4 people, 4-6 hrs. Beds |
2 | Biome Exploration Wall | Configure Irrigation, organize and plant ornamentals. | Needed: soil, mulch as above. | 3 teams, 3 each, mixed strength, |
| Culinary Program Planting | Organize and plant seeds, seedlings | Needed: Seeds, sets, soil, mulch and fertilizer. | 2 -4 teams including program participants + horticultural helpers. 4 – 8 hrs |
| Human Uses |
|
|
|
| Handwashing | Basin on pedestal by greenhouse. | Recycled, install graywater line. | 1 plumber, 1 helper. 3 hrs. |
| Quiet Spaces | Benches | We have them, Place them as desired. | Teams include youth, senior, activity leaders & participants. |
| Outdoor Meeting | Tables | We have them place them as desired. | Teams include youth, senior, activity leaders & participants. |
| Mobile Stage | modules | Needed: 6 modules on casters (24) o 2x6x12 pine – 24 o 2x4x12 pine - 18
| 2 teams: cutters & assemblers 4 people each, 8 hrs. |
| Outdoor Program Integration | Sports & other activity | Unidentified, but important needs | Teams include members of all programs. |
SYLCentral Y Gardens Establishment Plan
Asberry Spring 2010